Construction Progress

Phase 1 development of Balasaheb Deoras Rugnalay's new facility

60%

Overall Progress

7/7

Floors Completed

October 2026

Expected Completion

300+

Bed Capacity

Project Timeline

Medical equipment installation

Upcoming

Medical equipment installation will start from March 2026

Foundation Work Completed

June 2023

Successfully completed the foundation work, marking a significant milestone in our construction journey.

Ground Floor Structure

September 2023

Completed the ground floor structure, including the emergency department framework.

Seventh Floor Construction

Work completed on October 2025

Currently working on the seventh floor slab.

Interior Work

In Progress

Interior work started in November 2025, and currently it is in progress.

Recent Updates

Hon. Home Minister's Visit
July 04, 2025

Hon. Home Minister's Visit

Hon. Home Minister of India Shri Amitbhai Shah visited the Balasaheb Deoras Rugnalay construction site and reviewed the ongoing work of the Hospital and plans ahead.

Elevations
January 15, 2024

Elevations

Finalized the updated building Elevations .

project status as of 05-November-2025
November 05, 2025

project status as of 05-November-2025

project status as of 05-November-2025

Upcoming Milestones

Interior Work Phase 1

work started November 2025

Medical Equipment Installation

Planned for March 2026

Final Completion

Target: October 2026

×