Construction Progress
Phase 1 development of Balasaheb Deoras Rugnalay's new facility
70%
Overall Progress
7/7
Floors Completed
Dec 2026
Expected Completion
300+
Bed Capacity
Project Timeline
Medical equipment installation
UpcomingMedical equipment installation will start from September 2026
Interior Work
In ProgressInterior work started in Jan 2026, and currently it is in progress.
Seventh Floor Construction
RCC Work completed on December 2025All RCC work completed
Ground Floor Structure
September 2023, Completed the ground floor structure, including the emergency department framework.
Foundation Work Completed
June 2023Successfully completed the foundation work, marking a significant milestone in our construction journey.
Upcoming Milestones
Interior Work Phase 1
work started December 2025
Medical Equipment Installation
Planned for March 2026
Final Completion
Target: December 2026